Construction Updates and Coffee

Posted Friday, December 9

Construction Updates

The night work to tie in the new watermain that was scheduled to take place on Monday, Dec. 5, was rescheduled to Wednesday, Dec. 7, due to the rain on Monday and Tuesday. Crews did work on Wednesday night but ran into some complications working with the old cast iron pipes that are being replaced. On Thursday, Dec. 8, the night crews returned and were able to complete the work.