Construction Updates and Contaminated Soil

Posted Thursday, January 26

The warm January weather is perfect for the installation of the new curb and gutter along the south side of the street. Contractors just finished the installation of new sidewalk, driveways aprons, curb ramps and curb and gutter near the intersection of Stanhope Avenue, and are now installing the curb and gutter from Friendly Drive to Dan Allen Drive. Next week, weather permitting, crews will install the curb and gutter from Dan Allen Drive to Brooks Avenue and at Shepherd Street.