Updated Final Paving Schedule

Hillsborough Street construction image

Posted Wednesday, May 16

Pre-paving operations are scheduled for Saturday, May 19, during a daytime Hillsborough Street closure between Gardner Street and Faircloth Street. During the street closure, crews are scheduled to repair damaged curb and gutter along the corridor and complete any storm drain and manhole repairs and adjustments that need to take place.

Starting Sunday night, May 20, through Thursday, May 24, a series of nighttime street closures are scheduled while the final paving operations take place on the westbound lane.

Sunday night, June 3, through Thursday night, June 7, a series of nighttime street closures are scheduled for final paving operations to take place on the eastbound lane of the street.

Starting on Monday, June 11, final pavement will be placed on side streets affected by Hillsborough Street construction activity. The side streets will be paved during the daytime hours and will require intermittent closures along the streets that are being repaved.