Schedule Items: 
Work continues on Daisy Street replacing the sanitary sewer line and watermain in the intersection of Hillsborough Street and Daisy Street
PSNC is relocating gas lines at Friendly Drive
Duke continues their work transferring powerlines to underground conduits in preparation for pole removal later this month
Night work continues installing water services along the corridor
Paving operations are scheduled between Brooks and Friendly Drive
CCS is completing some cable work at Friendly Drive
Grading operations in preparation for paving at different location along the corridor