Phase II Schedule

Weekly Schedule

Jul 22 - Jul 28

Schedule Page Upper Alerts

Due to weather conditions and other unforeseen circumstances, the construction schedule is subject to change.

Schedule

    Saturday, July 22, 2017
    • No work is scheduled
    Sunday, July 23, 2017
    • A night crew is scheduled to install sewer services between Brooks Avenue and Gardner Street
    Monday, July 24, 2017
    • Storm drainage installation continues between Dixie Trail and Bagwell Avenue
    • Installation of sanitary sewer continues between Bagwell Avenue and Brooks Avenue
    • The night crew is scheduled to install a water main across Hillsborough Street to Brooks Avenue
    Tuesday, July 25, 2017
    • Storm drainage installation continues between Dixie Trail and Bagwell Avenue
    • Installation of sanitary sewer continues between Bagwell Avenue and Brooks Avenue
    • PSNC is scheduled to relocate a gas line on Brooks Avenue
    • The night crew is scheduled to start installing a water main and sewer main on Brooks Avenue
    Wednesday, July 26, 2017
    • A crew is scheduled to start installing storm drains from Gardner Street to Brooks Avenue
    • Installation of sanitary sewer continues between Bagwell Avenue and Brooks Avenue
    • PSNC is scheduled to relocate a gas line on Brooks Avenue
    • The night crew is scheduled to continue installing a water main and sewer main on Brooks Avenue
    Thursday, July 27, 2017
    • A crew is scheduled to continue installing storm drains from Gardner Street to Brooks Avenue
    • Installation of sanitary sewer continues between Bagwell Avenue and Brooks Avenue
    • The night crew is scheduled to continue installing a water main and sewer main on Brooks Avenue
    Friday, July 28, 2017
    • Installation of sanitary sewer continues between Bagwell Avenue and Brooks Avenue
    • A crew is scheduled to continue installing storm drains from Gardner Street to Brooks Avenue

Schedule Page Lower Alerts

Looking Ahead:

The Intersection of Founders Drive and Brooks Avenue is scheduled to be closed July 31, through August 3, while asphalt stamping takes place 

 


Long Term
Four Phase Approach

PHASE I, JUNE 2016 - SPRING 2017
HILLSBOROUGH STREET SOUTH SIDE

  • Sanitary Sewer and water
  • Duct Bank
  • Storm Drain
  • Power, telephone, and cable to duct bank
  • Street and sidewalk construction
  • Street light foundations
  • Remove old poles

PHASE II, SUMMER 2017
HILLSBOROUGH STREET NORTH SIDE

  • Storm Drain
  • Demo and grading for new sidewalks
  • Street and sidewalk construction
  • Street light foundations

PHASE III, FALL 2017
INSTALLATION OF ROUNDABOUTS

  • Pavement removal
  • Curb and truck apron
  • Wedging in roundabouts

PHASE IV, FALL 2017 - SPRING 2018
FINAL STAGE

  • Median construction
  • Final paving
  • Landscape
  • Pavement markings and signage