Schedule Page

Schedule Page Title Area

Phase II Schedule

Weekly Schedule

Apr 23 - Apr 29

Schedule Page Upper Alerts

Construction schedules are subject to change, due to weather conditions and other unforeseen circumstances. 

Schedule

    Monday, April 23, 2018
    • A crew is scheduled to start construction of the Dixie Trail roundabout
    • Southern Gardens is scheduled to plant trees, bushes and ground cover along the corridor
    Tuesday, April 24, 2018
    • A crew is scheduled to continue installing the new roundabout at Dixie Trail
    • Crews are schedule to continue planting tress, bushes and ground cover along the corridor
    Wednesday, April 25, 2018
    • Electrical conversions are scheduled
    • A crew is scheduled to continue installing the new roundabout at Dixie Trail
    • Crews are schedule to continue planting tress, bushes and ground cover along the corridor
    Thursday, April 26, 2018
    • A crew is scheduled to continue installing the new roundabout at Dixie Trail
    • Crews are schedule to continue planting tress, bushes and ground cover along the corridor
    Friday, April 27, 2018
    • Crews are schedule to continue planting tress, bushes and ground cover along the corridor
    • A crew is scheduled to continue installing the new roundabout at Dixie Trail
    Saturday, April 28, 2018
    • No work is scheduled
    Sunday, April 29, 2018
    • No work is scheduled

Schedule Page Lower Alerts

Looking Ahead;

  • The Dixie Trail roundabout is scheduled to be completed in early May

 

 


Long Term
Four Phase Approach

PHASE I, JUNE 2016 - SPRING 2017
HILLSBOROUGH STREET SOUTH SIDE

  • Sanitary Sewer and water
  • Duct Bank
  • Storm Drain
  • Power, telephone, and cable to duct bank
  • Street and sidewalk construction
  • Streetlight foundations
  • Remove old poles

PHASE II, SUMMER 2017
HILLSBOROUGH STREET NORTH SIDE

  • Storm Drain
  • Demo and grading for new sidewalks
  • Street and sidewalk construction
  • Streetlight foundations

PHASE III, WINTER - SPRING 2018
INSTALLATION OF ROUNDABOUTS

  • Pavement removal
  • Curb and truck apron
  • Wedging in roundabouts
  • Median construction

PHASE IV, SPRING 2018
FINAL STAGE

  • Final paving
  • Landscape
  • Pavement markings and signage