Schedule Page

Schedule Page Title Area

Phase II Schedule

Weekly Schedule

May 25 - May 31

Schedule Page Upper Alerts

Due to weather conditions and other unforeseen circumstances, the construction schedule is subject to change.

Schedule

    Thursday, May 25, 2017
    • Carolina Conduit Systems is scheduled to continue installing telecommunication lines across Friendly Drive
    • Fred Adams is scheduled to start installation of the brick sidewalk at Brooks Avenue and Founders Drive
    • The night crew will continue installing new water services to businesses along the north side of the street
    • Crews will continue grading work at Brooks Avenue and Founders Drive in preparation for paving operations on Friday
    Friday, May 26, 2017
    • Carolina Conduit Systems is scheduled to continue installing telecommunication lines across Friendly Drive
    • Paving operations are scheduled for the intersection of Brooks Avenue and Founders Drive
    • Crews will continue grading work at Brooks Avenue and Founders Drive in preparation for paving operations
    Saturday, May 27, 2017
    • Fred Adams is scheduled to continue installation of the brick sidewalk at Brooks Avenue and Founders Drive
    • Carolina Conduit Systems is scheduled to continue installing telecommunication lines across Friendly Drive
    Sunday, May 28, 2017
    • The night crew will continue installing new water services to businesses along the north side of the street
    Monday, May 29, 2017
    • The night crew will continue installing new water services to businesses along the north side of the street
    • Grading work continues at the Brooks Avenue intersection at Founders Drive
    Tuesday, May 30, 2017
    • Fred Adams is scheduled to install the brick sidewalk at Brooks Avenue and Founders Drive
    • Duke Energy Progress is scheduled to continue the installation of street lights along the south side of Hillsborough Street
    • The night crew will continue installing new water services to businesses along the north side of the street
    Wednesday, May 31, 2017
    • Fred Adams is scheduled to install the brick sidewalk at Brooks Avenue and Founders Drive
    • Fred Adams will have a crew at Friendly Drive installing the brick sidewalk
    • Duke Energy Progress is scheduled to continue the installation of street lights along the south side of Hillsborough Street
    • The night crew will continue installing new water services to businesses along the north side of the street

Schedule Page Lower Alerts

Looking Ahead:

  • The water main work at Daisy Street will resume 
  • Construction activities will switch to the north side of the street in June

 


Long Term
Four Phase Approach

PHASE I, JUNE 2016 - SPRING 2017
HILLSBOROUGH STREET SOUTH SIDE

  • Sanitary Sewer and water
  • Duct Bank
  • Storm Drain
  • Power, telephone, and cable to duct bank
  • Street and sidewalk construction
  • Street light foundations
  • Remove old poles

PHASE II, SUMMER 2017
HILLSBOROUGH STREET NORTH SIDE

  • Storm Drain
  • Demo and grading for new sidewalks
  • Street and sidewalk construction
  • Street light foundations

PHASE III, FALL 2017
INSTALLATION OF ROUNDABOUTS

  • Pavement removal
  • Curb and truck apron
  • Wedging in roundabouts

PHASE IV, FALL 2017 - SPRING 2018
FINAL STAGE

  • Median construction
  • Final paving
  • Landscape
  • Pavement markings and signage