Schedule Page

Schedule Page Title Area

Phase II Schedule

Weekly Schedule

Feb 21 - Feb 27

Schedule Page Upper Alerts

Construction schedules are subject to change, due to weather conditions and other unforeseen circumstances. 

Schedule

    Wednesday, February 21, 2018
    • Storm drain work is scheduled to continue on Daisy Street
    • A crew is scheduled to continue work in front of East Village Grill & Bar installing storm drains and grading the parking lot
    Thursday, February 22, 2018
    • A crew is scheduled to continue work in front of East Village Grill & Bar installing storm drains and grading the parking lot
    • Storm drain work is scheduled to continue on Daisy Street
    • A crew is scheduled to install sidewalk at Dixie Trail in front of East Village Grill & Bar
    Friday, February 23, 2018
    • Friday night the Street is scheduled to be closed to through traffic while crews implement a temporary traffic shift, remove traffic signals, and re-stripe the roadway.
    • Grading operations are scheduled to continue at East Village Grill & Bar
    • Storm drain work is scheduled to continue on Daisy Street
    • A crew is scheduled to install sidewalk at Dixie Trail in front of East Village Grill & Bar
    Saturday, February 24, 2018
    • The Street is scheduled to be closed to through traffic while crews implement a temporary traffic shift.
    • A crew is scheduled to install brick sidewalks at Daisy Street and near Pantana's Pool Hall
    Sunday, February 25, 2018
    • The Street is scheduled to be closed to through traffic while crews implement a temporary traffic shift.
    Monday, February 26, 2018
    • A crew is scheduled to resume work on the new roundabout at Rosemary Street
    • Storm drain work is scheduled to continue on Daisy Street
    • A crew is scheduled to install brick sidewalks at Daisy Street
    • A crew is scheduled to work on a retaining wall at Dixie Trail
    Tuesday, February 27, 2018
    • Storm drain work is scheduled to continue at Daisy Street
    • A crew is scheduled to continue work on the new roundabout at Rosemary Street
    • A crew is scheduled to work on a retaining wall at Dixie Trail

Schedule Page Lower Alerts

Looking Ahead;​​

  • Roundabout at Shepherd Street and Rosemary Street will be completed
  • Roundabout installation will begin at Brooks Avenue 

 

 


Long Term
Four Phase Approach

PHASE I, JUNE 2016 - SPRING 2017
HILLSBOROUGH STREET SOUTH SIDE

  • Sanitary Sewer and water
  • Duct Bank
  • Storm Drain
  • Power, telephone, and cable to duct bank
  • Street and sidewalk construction
  • Streetlight foundations
  • Remove old poles

PHASE II, SUMMER 2017
HILLSBOROUGH STREET NORTH SIDE

  • Storm Drain
  • Demo and grading for new sidewalks
  • Street and sidewalk construction
  • Streetlight foundations

PHASE III, WINTER - SPRING 2018
INSTALLATION OF ROUNDABOUTS

  • Pavement removal
  • Curb and truck apron
  • Wedging in roundabouts
  • Median construction

PHASE IV, SPRING 2018
FINAL STAGE

  • Final paving
  • Landscape
  • Pavement markings and signage