News and Updates, December Week One

The Hillsborough Street Renewal Project, Phase II is highlighted in the newest release of Under Construction, a program produced by the City of Raleigh each quarter highlighting City of Raleigh construction projects. 

Night Work Kept to a Minimum during Finals
Contractors are trying to keep night work along the corridor to a minimum during the next two weeks while students prepare for final examinations. However, there are a couple of tasks that require night work.

Currently, Monday, December 5, crews do plan to work during the nighttime hours and will have Hillsborough Street closed to through traffic. Crews will be working at Concord Street and Rosemary Street on the critical watermain operations to tie in the new watermain.