Schedule Items: 
A night crew is scheduled to coninue work at Daisy Street installing a new watermain
A night crew is scheduled to continue connecting water services along the corridor
A crew is scheduled to continue installing the brick sidewalk at Reader's Corner
The trolley rails are scheduled to be installed on the rain garden at the 2811 Building
The fence on the new retaining wall at Fincastle Apartments is scheduled for installation