Monday, April 17

Date: 
Monday, April 17, 2017
Schedule Items: 
Work continues on Daisy Street replacing the sanitary sewer line and watermain
A crew will continue installing brick sidewalks between Rosemary Street and Concord Street
Duke continues removing utility poles between Concord Street and Stanhope Avenue
Work is scheduled to take place on the retaining wall at Fincastle Apartments
Night work continues, installing water services along the corridor